Statutory certificate lodgement guide

The steps from preparing your documents to the final Occupation Certificate, including the NSW Planning Portal, neighbour notice and inspections.

  1. Step 01

    Prepare your documents

    Plans, reports and certificates

    Collect the architectural plans, survey, engineering details, BASIX certificate and your lot's section 10.7 planning certificate. Before lodgement, we review these against the planning standards and the National Construction Code.

  2. Step 02

    Lodge on the NSW Planning Portal

    Online application

    Your application for a Complying Development Certificate (CDC) or Construction Certificate (CC) is lodged through the NSW Planning Portal, with CertifiBuild nominated as the certifier. We check that the application and fees are complete.

  3. Step 03

    Assessment and certificate

    CDC or CC issued before work starts

    We review the plans and list any gaps in writing. For many metropolitan CDCs, neighbours within 20 metres have to be notified no less than 14 days ahead of the certificate being issued. When everything complies, the CDC or CC is issued.

  4. Step 04

    Before work starts

    Principal Certifier and notices

    You appoint a Principal Certifier, then lodge a notice of commencement no later than 2 days before the work starts. With a CDC, neighbours within 20 metres must also be informed before work begins: 7 days ahead or more in metropolitan areas, or 2 days ahead in regional, rural and release areas.

  5. Step 05

    Critical stage inspections

    Inspections as the build progresses

    Your builder books every required inspection, for example footings, slab, frame, waterproofing of wet areas and stormwater. Nothing is covered until that stage has passed inspection.

  6. Step 06

    Final inspection and OC

    Occupation Certificate

    We issue the Occupation Certificate after the final inspection is complete and every required certificate has been provided (such as glazing, smoke alarms and engineering sign-offs). From then, the building may be occupied or used.

Key requirements to keep in mind

In NSW, development requires the correct approval under the Environmental Planning and Assessment Act 1979, and building work has to comply with the National Construction Code. Notice periods differ depending on location and the kind of work, so we confirm them for your project.

Which certificates can CertifiBuild issue?

Our registered certifiers issue Complying Development Certificates (CDC), Construction Certificates (CC) and Occupation Certificates (OC), and act as Principal Certifier, for Class 1 buildings and Class 10 structures.

Do I need to lodge on the NSW Planning Portal myself?

You or your designer can lodge directly, nominating CertifiBuild as the certifier. We can guide you through the steps.

Ready to start?

You will get a list of the documents required, along with a written fee proposal.