Occupation certificates in NSW
The last approval before a new building is lived in or used. Plan for it early and the finish line stays clear.
OC at a glance
The step between finishing and moving in
Until an occupation certificate is in place, nobody may occupy or use a newly erected building or any new section of one. Your principal certifier issues it following the last inspection, once both the work and the completion documents meet the approval.
Builder handover is a separate matter. Getting practical completion and the keys does not authorise occupation. Only the OC does.
Talk to us about completionRequired before use
Occupation or use must wait until the certificate is issued.
Issued by the principal certifier
The certifier appointed for the build determines the OC.
Documents count
Along with the building, trade certificates and condition evidence are reviewed.
No retrospective approval
An OC cannot cover work that departs from the approval.
A clear way forward
How an OC is reached
Most of the work toward an OC happens during construction, not at the end.
01
Inspections kept up
Each mandatory stage gets its inspection on time while construction is under way.
02
Documents collected
Installer and trade certificates are collected as each stage of work wraps up.
03
Changes raised early
Any variation to the approved plans is dealt with before it is built.
04
Final inspection
When construction ends, we inspect the completed building and check it matches the approval.
05
Items resolved
Outstanding documents or defects are provided or fixed and checked.
06
OC determined
When every requirement is satisfied, the occupation certificate is issued.
Completion evidence
Documents often needed for an OC
The exact list comes from your approval. These are the most common for homes and outbuildings.
- Inspection recordResults of every required critical stage inspection.
- Trade certificatesWaterproofing, glazing, smoke alarm and similar certificates.
- BASIX evidenceProof the BASIX commitments, such as fixtures and tanks, were installed.
- Condition evidenceAnything the approval requires before occupation, such as authority sign-offs.
Project-specific pricing
Part of your certification.
Where we are your principal certifier, the final inspection and OC are included in the scope we quote at appointment.
- Final inspection
- Documents to review
- Any reinspections
- Project type
What are you planning?
Projects that need an OC.
New homes, additions and most Class 10 structures built under a CC or CDC need an OC.
Certain minor work needs no OC. Ask your principal certifier whether your project requires one.
Common issues
What holds an OC up
Most hold-ups near completion come down to three issues.
The paperwork
Missing certificates
A single missing trade certificate can hold up the whole OC.
The design
Unapproved changes
Work that differs from the approved plans may need a further approval first.
The inspections
A skipped stage
If a mandatory inspection was missed, the OC may not be able to be issued at all.
At the end of your build
What happens before you can move in?
An occupation certificate (OC) is the document that says your new home or structure is fit to use. The rules changed on 1 December 2019. Here is how they work now, and what helps the final weeks of a build go smoothly.
Sources: NSW DPIE: Occupation certificates fact sheet (via Hornsby Council); NSW Planning Portal: Occupation certificate; NSW Planning: Issue BASIX completion receipt; Building Commission NSW: FAQs for building certifiers; ABCB: Housing Provisions (NCC 2022), Part 9.5. General information only; requirements depend on your lot, design and approval.
Moving in before everything is finished
NSW used to issue interim and final OCs. Since 1 December 2019 there is just one type of occupation certificate. You may still see "interim" or "final" in older approval conditions, but they only apply to approvals issued before that date.
A partial OC may still be issued for whichever section of the building is ready to use. The unfinished work must not create a health or safety risk, and your approval must not rule it out. The certificate must clearly show which part it covers. You then have five years to get an OC for the whole building.
What the certifier looks at
Before issuing an OC, your principal certifier (the certifier in charge of your job) must be satisfied of several things. Your approval must still be in force. A construction certificate must have been issued, if one was needed. The finished work must match the approval. Any conditions due before move-in must be met. And under the building code, the building has to be suitable for use.
There is no limit on how many OCs a project can have, but each one must meet every requirement. Your certifier keeps records of why each certificate was issued.
BASIX and smoke alarms
If your home has a BASIX certificate (the NSW energy and water rating for homes), your certifier is required to issue a BASIX completion receipt. This step sits between the last inspection and the OC. It confirms the home was built to match the BASIX certificate.
A new house needs smoke alarms that meet AS 3786. They must run on mains power if the house has it, and be interconnected where two or more are installed. Each hallway that serves bedrooms needs one. With no hallway, place one between the bedrooms and the other parts of the house. Every storey without bedrooms needs one too. Alarms go on or near the ceiling, away from dead air pockets.
How do I apply?
You apply for an OC online via the NSW Planning Portal and upload the supporting documents. Councils have had to use the Portal since 1 July 2021. Have your inspection records, trade certificates and BASIX details ready before you apply. That avoids delays from requests for more information.
When the certificate is held back
A principal certifier has no discretion to issue an OC while any requirement is still unmet. Building Commission NSW expects certifiers to tell the applicant as soon as they become aware of a problem, so it can be sorted while trades are still on site rather than after they have left.
The reverse also holds. Once every requirement has been satisfied and the fees are paid, a certifier cannot refuse the certificate. If you are unsure why yours is on hold, ask for the outstanding items in writing and work through them one by one.
Site items that can delay the OC
Some conditions reach beyond the house itself. Depending on your approval, landscaping, fencing or the driveway may have to be completed first, before any OC is issued. Bins and utility connections also need to be in place.
Read your conditions early in the build and mark each one tied to occupation. Items such as a driveway crossing or a condition requiring planting are easy to leave until the end, and they are often handled by trades other than your builder.
Lenders, final payment and handover
With a construction loan, your lender is likely to want the OC before it releases the last payment to the builder. It may also ask for your home insurance policy and the builder's final invoice, and send a valuer to look at the house. Ask the lender early which documents it needs.
Moving in before the final payment is made puts you in breach of the building contract, unless the builder has agreed in writing. Treat the OC, the final payment and the handover as one connected sequence, with the OC first.
Using a building without an OC
Living in or using a new building that needs an OC before one is issued is an offence. Councils can respond with penalties, notices and orders.
The risk extends to a partly finished home. If only some rooms are ready, the lawful way to use them early is a partial OC covering that part, not simply moving furniture in. Talk to your certifier about this before the final stages, while the documents for the finished section can still be gathered.
After the OC is issued
An OC reflects the inspections and records the certifier held on the day it was issued. Compliance from then on, including later changes to the building, falls to the council, not the certifier.
The issue date can matter for your warranties as well. The NSW Government's home building guidance explains that statutory warranty periods run from completion, being the earlier of handover of possession or the OC being issued. Report any defects to your builder in writing as soon as they show up, with photos.
Pools, property sales and tenancies
Selling a home that has a pool brings extra paperwork. The vendor must attach the pool's registration certificate to the contract, plus one more document: an OC issued recently, a current compliance certificate under the pool laws, or a non-compliance certificate. Leave these out and the purchaser may have a right to cancel within the first 14 days after exchange, provided settlement has not taken place.
For a rental, the landlord must supply the tenant with the pool's compliance certificate or its OC. A non-compliance certificate is not enough to lease the home. Compliance certificates expire after 3 years, so keep track of that date if you plan to lease the home later.
More sources: Building Commission NSW: FAQs for building certifiers; NSW Planning Portal: MyHome Planner, post-build; City of Newcastle: The principal certifier, inspections and occupation certificates; NSW Government: Owning a pool or spa, your obligations. General information only; requirements depend on your lot, design and approval.
Your questions, answered
Occupation certificates, explained.
Questions owners commonly ask as their build nears completion.
Ask us about your projectIs an OC still required after a CDC?
In most cases, yes. A complying development certificate (CDC) approves the building work, but it does not let anyone live in or use the new building. That permission comes from the OC, which the principal certifier issues after the final inspection. You can apply for it within the existing CDC record on the NSW Planning Portal or as a separate application. Some minor structures may not need an OC, so check your CDC conditions and ask your principal certifier early, while the completion paperwork can still be planned around the build.
Who issues the OC?
Only the principal certifier appointed for the building work can issue the OC. That may be the council or a registered certifier, depending on whom the owner appointed. Whoever approved your CC or CDC plays no part in the OC unless they also hold the principal certifier appointment. The last site inspection must be done by the principal certifier, not delegated, and it is followed by a review of the inspection records and completion documents. If the certifier was replaced during the build, the replacement makes the decision, relying on the records passed across.
Can we occupy the home before the OC?
No. If your project needs an OC, nobody may move into the home or start using any new part of it before the certificate is in hand. Doing so is an offence and can lead to penalties, notices or orders from council. Reaching practical completion or collecting keys from the builder does not change that. If one section is ready sooner, ask whether a partial OC is possible. Moving in before the final payment can also put you in breach of your building contract, absent the builder's written consent, so line up both steps.
Can part of a building get an OC?
Yes. A partial OC can be issued for a finished section when the remaining work poses no health or safety risk and no condition of the approval rules it out. The certificate names the part it covers, and you may only occupy that part. An OC for the whole building must follow within five years of the partial one. Each OC has to meet every requirement on its own, so the inspections and documents for the finished section need to be complete. Raise the idea with your certifier well before the final stages.
How long does an OC take?
There is no fixed timeframe. Timing turns on how large and complex the job is, and how quickly the remaining requirements are met. The final inspection is arranged once you apply, and most delays trace back to missing certificates, unfinished condition items or defects found at that visit. Collect each trade's certificate when its work wraps up, confirm conditions such as landscaping or driveway works are done, and check that utilities and bins are in place before booking. A complete package lets the certifier decide without a second visit.
Getting to completion
Related services.
Guidance: the National Construction Code. Requirements depend on your approval and conditions.
Guides
Occupation certificate guides
Interim and final occupation certificates: the difference
Why an occupation certificate gets held up
Occupation certificates: what you need before moving in
Where we work
Occupation certificates across NSW
We work in 39 council areas, from Newcastle and the Central Coast through Greater Sydney and the Blue Mountains to Lithgow, the Southern Highlands and the Illawarra. Local rules shape every approval, so start with your council or suburb.
Council areas
- Canterbury-Bankstown Council
- Central Coast Council
- City of Ryde
- Lane Cove Council
- Shellharbour City Council
- Wingecarribee Shire Council
- Wollondilly Shire Council
- Woollahra Municipal Council
Local planning notes by suburb
See all 39 council areasNearly finished?
A straightforward route to moving in.
Let us know your approval type, how far construction has progressed and who the principal certifier is. We'll explain the next steps.